There are several transportation updates around the Conroe and Montgomery area. Check them out below. This list is not comprehensive.

Ongoing projects

Hwy. 105 widening

Project: Between 10th Street and South Loop 336, Hwy. 105 is being widened from two to four lanes.

Update: This project is 60% complete, according to the Texas Department of Transportation’s March 10 media update.

  • Timeline: March 2023-second quarter 2028
  • Cost: $52.65 million
  • Funding source: state funds

South Loop 336 widening

Project: South Loop 336 is being widened from two to four lanes with a continuous left-turn lane between I-45 and Ladera Creek Trace.

Update: This project is 62% completed, according to TxDOT’s March 10 media update.

  • Timeline: November 2024-third quarter 2027
  • Cost: $20.57 million
  • Funding source: state funds

South Loop 336 lighting

Project: This project entails safety lights, conduit and other electrical services along South Loop 336 between I-45 and Sgt. Ed Holcomb Boulevard.

Update: According to TxDOT’s March 10 media update, this project is 98% completed.

  • Timeline: December 2024-second quarter 2026
  • Cost: $518,164
  • Funding source: state funds

I-45 LED installation

Project: High mast LED lights are being installed along the main lanes of I-45 between FM 830 and Shepard Hill Boulevard.

Update: This project is 91% complete, according to TxDOT’s March 10 media update.

  • Timeline: February 2025-second quarter 2026
  • Cost: $1.45 million
  • Funding source: state funds

FM 1097 widening

Project: FM 1097 is being widened from two to four lanes with a continuous left-turn lane between west of Blueberry Hills Road to Lake Conroe Hills Drive.

Update: According to TxDOT’s March 10 media update, this project is 90% completed.

  • Timeline: second quarter 2022-second quarter 2026
  • Cost: $20.21 million
  • Funding sources: federal, state funds

FM 1097 at Atkins Creek project

Project: This project at the intersection of Atkins Creek and FM 1097 entails culvert replacement, shoulder additions and other improvements.

Update: This project is 67% complete, according to TxDOT’s March 10 media update.

  • Timeline: third quarter 2025-third quarter 2026
  • Cost: $4.41 million
  • Funding sources: federal, state funds

I-45 direct connector

Project: A direct connector is being constructed to connect northbound I-45 with eastbound Hwy. 242.

Update: This project is 22% completed, according to a March 10 media update from TxDOT.

  • Timeline: second quarter 2025-third quarter 2028
  • Cost: $42.63 million
  • Funding sources: federal, state funds