Work is underway on several Willis ISD projects, including the construction of new campuses. See the latest updates below.
Ninth-grade center
- Project: The center is a new expansion project for Willis High School as well as the parking lot.
- Update: Permits are waiting to be approved and breaking ground to begin soon, WISD Chief Operations Officer Bob Eaton said at the Nov. 12 meeting.
- Location: 10005 Hwy. 75, Willis
- Timeline: fall 2027 completion
Elementary School No. 7
- Project: The new elementary campus, funded by WISD’s $143 million 2022 bond, will have an 850-student capacity.
- Update: The district has the exterior up and is getting the interior ready. Permits have been submitted to Montgomery County, Eaton said.
- Location: 8150 M.P. Clark Road, Conroe
- Timeline: spring 2025-August 2026
Transportation Center
- Project: The new center will accommodate 100 buses along with staff offices.
- Update: The project was paused due to budgetary restraints, Eaton said.
- Location: 215 Philpot St., Willis
- Timeline: spring 2026 completion
By Angela Bonilla
Education Reporter
Angela joined Community Impact as a reporter covering education in Montgomery County in April 2024 after working as a journalist in Central Texas. Prior to joining CI, Angela worked as part of a digital and social media team at a news station in Waco. When she’s not writing, she enjoys reading, playing with makeup, watching reality TV and going to the library.