There are several transportation updates around the Conroe and Montgomery area. Check them out below. This list is not comprehensive.

Ongoing projects

I-45 direct connector

Project: A direct connector is being constructed to connect northbound I-45 with eastbound Hwy. 242. This project also includes drainage improvements.

Update: This project is 20% completed, according to a Feb. 18 media update from the Texas Department of Transportation.

  • Timeline: second quarter 2025-third quarter 2028
  • Cost: $42.63 million
  • Funding sources: federal, state funds

I-45 HOV lane extension

Project: The high-occupancy vehicle lane of I-45 between FM 1488 and South Loop 336 is being extended.

Update: This project is 79% completed, according to TxDOT’s Feb. 18 media update.

  • Timeline: second quarter 2025-first quarter 2026
  • Cost: $1.26 million
  • Funding sources: federal, state funds

Hwy. 105 widening

Project: Between 10th Street and South Loop 336, Hwy. 105 is being widened from two to four lanes.

Update: Per TxDOT’s Feb. 18 media update, this project is 60% completed.

  • Timeline: March 2023-second quarter 2028
  • Cost: $52.65 million
  • Funding source: state funds

South Loop 336 widening

Project: South Loop 336 is being widened from two to four lanes with a continuous left-turn lane between I-45 and Ladera Creek Trace.

Update: This project is 62% completed, according to TxDOT’s Feb. 18 media update.

  • Timeline: November 2024-third quarter 2027
  • Cost: $20.57 million
  • Funding source: state funds

FM 1097 widening

Project: Between west of Blueberry Hills Road to Lake Conroe Hills Drive, FM 1097 is being widened from two to four lanes with a continuous left-turn lane.

Update: This project is 90% completed, according to TxDOT’s Feb. 18 media update.

  • Timeline: second quarter 2022-second quarter 2026
  • Cost: $20.21 million
  • Funding sources: federal, state funds

FM 1097 at Atkins Creek project

Project: This project at the intersection of FM 1097 and Atkins Creek includes culvert replacement, shoulder additions and overlay.

Update: According to TxDOT’s Feb. 18 media update, this project is 67% completed.

  • Timeline: third quarter 2025-third quarter 2026
  • Cost: $4.41 million
  • Funding sources: federal, state funds

Hwy. 105 reconstruction

Project: From South Loop 336 to FM 1484, Hwy. 105 is being reconstructed and widened from two to four lanes.

Update: This project is 91% completed, according to TxDOT’s Feb. 18 media update.

  • Timeline: February 2023-first quarter 2026
  • Cost: $90.81 million
  • Funding source: state funds

I-45 LED installation

Project: High-mast LEDs are being installed along the mainlanes of I-45 between FM 830 and Shepard Hill Boulevard.

Update: According to TxDOT’s Feb. 18 media update, this project is 91% completed.

  • Timeline: February 2025-first quarter 2026
  • Cost: $1.45 million
  • Funding source: state funds

Hwy. 242 widening

Project: Existing right of way on Hwy. 242 between FM 1488 and I-45 is being used to widen lanes and restripe the intersections.

Update: As of TxDOT’s Feb. 18 media update, the project is 79% complete.

  • Cost: $29.11 million
  • Timeline: October 2023-fourth quarter 2026
  • Funding sources: federal, state funds

Completed projects

Anderson Road reconstruction

Project: Anderson Road was reconstructed to include additional roadway width and shoulders between FM 1097 and FM 830.

Update: This project was completed as of Feb. 20, Montgomery County Precinct 1 Commissioner Robert Walker announced via Facebook.

  • Timeline: Completed in February
  • Cost: $2.09 million
  • Funding source: Montgomery County road bond funds