There are several transportation projects in the works around the Conroe and Montgomery area. Check them out below. This list is not comprehensive.

Upcoming projects

Calvary Road reconstruction

Project: Calvary Road will be reconstructed to be a four-lane asphalt road between Lake Conroe Bay Road and I-45.

Update: This project is currently in the design phase, according to the Montgomery County Precinct 1 capital improvement projects dashboard.

  • Timeline: TBD
  • Cost: $1.01 million
  • Funding source: Montgomery County road bond funds

Cude Cemetery Road reconstruction

Project: Cude Cemetery Road will be reconstructed to be a four-lane asphalt road between FM 1097 and FM 830.

Update: This project is currently in the design phase, according to the Montgomery County Precinct 1 capital improvement projects dashboard.

  • Timeline: TBD
  • Cost: $872,040
  • Funding source: Montgomery County road bond funds

Lone Star Parkway reconstruction

Project: Lone Star Parkway will be reconstructed to be a four-lane asphalt road between FM 149 and Hwy. 105.

Update: This project is currently in the design phase, according to the Montgomery County Precinct 1 capital improvement projects dashboard.

  • Timeline: TBD
  • Cost: $1.02 million
  • Funding source: Montgomery County road bond funds

Ongoing projects

Lake Mount Pleasant reconstruction

Project: Additional width is being added to Lake Mount Pleasant Road between South Shore Drive and FM 1097.

Update: This project is under construction, per the Montgomery County Precinct 1 capital improvement projects dashboard.

  • Timeline: Construction on this project began in January, per a Jan. 20 Facebook post from Precinct 1 Commissioner Robert Walker.
  • Cost: $4.8 million
  • Funding source: Montgomery County road bond funds

Coaltown Road reconstruction

Project: Coaltown Road is being reconstructed to include additional roadway width between Rogers Road and Hwy. 75.

Update: Construction on this project is ongoing, according to the Montgomery County Precinct 1 capital improvement projects dashboard.

  • Timeline: Construction began in February, per a Feb. 6 Facebook post from Walker.
  • Cost: $4 million
  • Funding source: Montgomery County road bond funds

Johnson Road reconstruction

Project: Between FM 1486 and Bethel Road, Johnson Road is being reconstructed within its existing right of way to include extra width and shoulders.

Update: This project is underway, according to the Montgomery County Precinct 1 capital improvement projects dashboard.

  • Timeline: This project began construction in April, per an April 14 Facebook post from Walker.
  • Cost: $2.3 million
  • Funding source: Montgomery County road bond funds

Completed projects

Martin Luther King Drive reconstruction

Project: The two-lane road was reconstructed to add additional width and shoulders between FM 149 and FM 1097 West.

Update: This project has been completed, per an April 10 Facebook post from Walker.

  • Cost: $1.4 million
  • Funding source: Montgomery County road bond funds

Cedar Lane Segment 1

Project: Between McCrorey and County Line roads, the road was constructed to include additional width and shoulders.

Update: This project has been completed, per an April 8 Facebook post from Walker.

  • Cost: $2.1 million
  • Funding source: Montgomery County road bond funds