There are several transportation projects in the works around the Conroe and Montgomery area. Check them out below. This list is not comprehensive.
Upcoming projects
Calvary Road reconstruction
Project: Calvary Road will be reconstructed to be a four-lane asphalt road between Lake Conroe Bay Road and I-45.
Update: This project is currently in the design phase, according to the Montgomery County Precinct 1 capital improvement projects dashboard.
- Timeline: TBD
- Cost: $1.01 million
- Funding source: Montgomery County road bond funds
Cude Cemetery Road reconstruction
Project: Cude Cemetery Road will be reconstructed to be a four-lane asphalt road between FM 1097 and FM 830.
Update: This project is currently in the design phase, according to the Montgomery County Precinct 1 capital improvement projects dashboard.
- Timeline: TBD
- Cost: $871,289.54
- Funding source: Montgomery County road bond funds
Lone Star Parkway reconstruction
Project: Lone Star Parkway will be reconstructed to be a four-lane asphalt road between FM 149 and FM 2854.
Update: This project is currently in the design phase, according to the Montgomery County Precinct 1 capital improvement projects dashboard.
- Timeline: TBD
- Cost: $1.01 million
- Funding source: Montgomery County road bond funds
Old Plantersville Road reconstruction
Project: Old Plantersville Road will be reconstructed to include additional roadway width and shoulders between Hwy. 105 and Old Dobbin Road.
Update: This project is currently under review, according to the Montgomery County Precinct 1 capital improvement projects dashboard.
- Timeline: TBD
- Cost: $32,354.24
- Funding source: Montgomery County road bond funds
Ongoing projects
Anderson Road reconstruction
Project: Between FM 1097 and FM 830, Anderson Road is being reconstructed to add additional roadway width and shoulders.
Update: Construction is underway on this project, according to the Montgomery County Precinct 1 capital improvement projects dashboard.
- Timeline: Construction began Nov. 18, according to a Nov. 17 Facebook post from Precinct 1.
- Cost: $2.08 million
- Funding source: Montgomery County road bond funds
Lake Mount Pleasant Road reconstruction
Project: Between FM 1097 and Hidden Forest Drive, Lake Mount Pleasant Road is being reconstructed to add additional roadway width and shoulders.
Update: This project is currently under construction, according to the Montgomery County Precinct 1 capital improvement projects dashboard.
- Timeline: Construction began the week of Jan. 19, according to a Jan. 20 Facebook post from Precinct 1.
- Cost: $4.8 million
- Funding source: Montgomery County road bond funds
Hwy. 242 widening
Project: The Texas Department of Transportation is using the existing right of way on Hwy. 242 between FM 1488 and I-45 to widen lanes and restripe the intersections.
Update: As of the most recent information released by TxDOT in late January, the project being carried out by Posillico Civil Inc. was 74% complete.
- Timeline: Oct. 23, 2023-fourth quarter of 2026
- Cost: $29.11 million
- Funding sources: federal, state funds
Completed projects
Airport Road reconstruction
Project: Between Bushy Creek Bridge and FM 1484, Airport Road was reconstructed to add additional roadway width and shoulders.
Update: This project is completed, according to the Montgomery County Precinct 1 capital improvement projects dashboard.
- Cost: $248,506.76
- Funding source: Montgomery County road bond funds